10.27.23
Hoeven: FM Flood Protection Inlet Structure Serves as Hinge for First-in-the-Nation P3 Project
Milestone Completed Due to Senator’s Efforts to Secure Early Federal Funding
WASHINGTON – Senator John Hoeven today, along with Assistant Secretary of the Army for Civil Works Michael Connor and local leaders, marked the completion of the inlet structure for the Fargo-Moorhead region’s flood protection project. The inlet is a key element, tying together the local portion of the project with the federal portion, which is able to move forward due to Hoeven’s successful efforts to:
- Fully fund the $750 million federal cost share.
- Through his role on the Senate Energy and Water Development Appropriations Committee, Hoeven secured the first portion of this funding in 2016, which enabled construction of the inlet structure to begin.
- Hoeven then worked to secure the balance of the federal cost of the project, which received full funding in 2022.
- Advance this as the first major Army Corps project to utilize the public-private partnership (P3) split-delivery model and a Water Infrastructure Finance and Innovation Act (WIFIA) loan.
- Hoeven worked to advance the Fargo-Moorhead project as a proof-of-concept for the rest of the nation, while also ensuring projects that use alternative financing methods, like P3s, receive fair treatment during the Corps’ cost-benefit analysis.
In addition, Hoeven’s efforts have included:
- Working to pass 16 acts of Congress, including:
- 9 legislative provisions, such as the project authorization in 2014 and a new construction start authorization in 2016.
- 7 separate appropriations to fund the project’s construction.
- Coordinating efforts across four federal agencies.
- Providing funding and flexibility to concurrently raise I-29 and begin excavating the Red River Control Structure to keep the project on schedule.
- Helping renegotiate the Project Partnership Agreement to increase the federal funding commitment from $450 million.
- Resolving the easement issue on lands purchased with Hazard Mitigation Grant Program (HMGP) funding, allowing the project to use an alternative route.
-###-
Next Article Previous Article